Claridges Hotel

Date: Monday, May 13th, 2019

Claridges Hotel 13.05.19

M&E works are progressing well within our Claridges Hotel Victorian building refurbishment & have moved to an advanced stage of 2nd fix.

The works are taking place on multiple floors concurrently and we will soon be commencing testing & commissioning throughout the project.

Strategic room/ suite handovers have been agreed with our client to ensure there is maximum room inventory available ahead of the hotels notoriously busy summer period.

This is one of the many projects we are currently involved in with the Maybourne group and forms part of the future vision for the Hotel.

 

Electrical Services

  • Strip out/ removals
  • Switchgear and sub mains cabling
  • General purpose LED & emergency lighting
  • General Purpose Power
  • Electric underfloor heating
  • Fire Alarm
  • Structured cabling
  • CCTV
  • Access control
  • Mechanical wiring
  • Test & commission

Mechanical Services

  • Strip out/ removals
  • Heating and plumbing
  • Pipework testing
  • Thermal insulation
  • Installation of sanitary ware
  • Test & commission