Stena – VT4 and Loch Ryan
Victoria Terminal 4
The project consisted of the construction of Stena Lines new Victoria Terminal 4 within Belfast Harbour.
Loch Ryan
The project involved the construction of the new Loch Ryan Port development for Stena Line on a 26-acre site including reclaimed land 5 miles north of Stena’s existing Stranraer Port facilities.
Project Highlights
- Victoria Terminal 4
- The site incorporated a 4000m2 three storey bespoke terminal building, external workshops, ro-ro bridge, fuel terminal, remote check-in facilities and external lorry/ car parking all on a secure 32-acre site.
- The industrial workshop provides for both vehicles / ship repairs and maintenance and is fully fitted out with overhead crane, welding booths with specialized fume extract systems, compressed air and heated via high level gas fired heaters.
- The contract included the provision of the fuel farm which consisted of three fuel storage tanks and fuel transfer facilities to allow for the efficient refuelling of Stena’s vessels.
- The site was serviced via a new electrical transformer with all associated HV/LV cabling.
- There are 15 high mast lighting columns installed varying from 25-30 meters in height to cover the site and associated car parks and loading areas. The car parks are installed with fully automated access barriers and ticket booths.
Loch Ryan
- The new development incorporated terminal buildings, security building, workshop, check-in booths, pump house, link span and security gallery. The facility is open 24 hours a day, 7 days a week.
- There was extensive infrastructure works involved including alterations to the existing A77 road and creation of a new roundabout adjacent to the site. This involved the installation of new street lighting and the extension to the existing water main along the road network.
- The site itself included approx. 3000 metres of new mains water and fire main pipework supplying the various buildings, fire hydrants and ship to shore international connections.
- There was a site wide fibre network installed with four network rings, two dedicated to the CCTV installation and the remaining two for the data installation.
- There were 17 high mast lighting columns installed varying from 25-30 meters in height to cover the site and associated car parks and loading areas.
- Backup power to the terminal building is supplied by a new diesel fuelled generator. We also relocated the two existing 450kva and 150kva generators from the old Stranraer Terminal as back up for the workshop facilities and link span.
Client: Stena Line Limited
Main Contractor: McLaughlin and Harvey
Architect: Hobart & Heron
Consultant: Mott McDonald
Services: Mechanical & Electrical
Duration: 12 Month
Value: £2,320,000
Location: Belfast