UTV Fit-out

Date: Monday, November 20th, 2017

itv banner

 

We are currently working on the fit-out of the MEP services at UTV’s new offices and studio at Belfast Harbour. The eighth floor of the City Quays 2 building will have a high-definition studio, editing technology and offices.

Next year UTV will vacate its Havelock House premises on the Ormeau Road after nearly 60 years.

We were appointed for the project by principal contractor McLaughlin & Harvey. We have an ongoing and successful working relationship which has been developed over many years.

ITV - 20.11.17

M&E services include

  • Switchgear and sub mains cabling
  • UPS
  • Gas Suppression
  • Vesda System
  • General purpose & emergency lighting
  • General Purpose Power
  • Fire Alarm
  • Structured cabling
  • Intruder Alarm
  • Disabled Toilet Alarm
  • CCTV
  • Access control
  • Mechanical wiring
  • Test & commission

 

  • Primary supply and extract ductwork
  • Chilled water installation
  • Fan coil units
  • Cooling system
  • Leak detection
  • BMS installation
  • Plumbing
  • Sanitary Ware
  • Test & commission