Andrew Melville Hall, University of St. Andrews
Date: Tuesday, August 7th, 2018

We are now at the commissioning stage of our student’s accommodation project.
The accommodation extends to 273 bedrooms and are formed from a precast concrete structure. The building is Grade A listed and the project is sensitive to the requirements of Historic Environment Scotland and Fide Council.
Client: University of St Andrews
Main Contractor: Graham Construction
Architect: Cooper Cromar
Consultant: Atelier Ten
Services: M&E
Duration: 15 months
Value: £2,700,000
Location: St Andrews, Scotland
We are continually monitoring the commissioning progress against the programme both upstream and downstream with our supply chain.
Commissioning of Mechanical services:
- Low temperature hot water systems
- Ventilation balancing
- Fire damper testing
- Drainage testing
- Domestic water services
- BMS Controls commissioning
- AC commissioning
- Manuals & drawings
- Client demonstrations
Commissioning of Electrical services:
- Testing and verification (Dead and live testing)
- Fire Alarm
- Structured cabling
- Access Control
- CCTV
- General and emergency lighting
- Smoke ventilation
- Lightning Protection system
- Manuals & drawings
- Client demonstrations